(251) Press Releases » Statement of company JAVYS to the workplace accident ...

On the 9th of November, 2022, an employee of the Contractor, company VUJE, was injured at workplace in the premises of company JAVYS in Jaslovské Bohunice, in the building used by the Contractor for the performance of work.

(252) Press Releases » The Company JAVYS and IAEA agency signed the Agreement on Collaborating Centre

The company JAVYS joined the "club" of Collaborating Centres with the International Atomic Energy Agency (IAEA), and in the field of nuclear facilities decommissioning, Slovakia became the third country with which the IAEA signed a cooperation agreement.

(253) News » The Company JAVYS, a. s.

Selection procedure for the Chairman of the Board of Directors of the company JAVYS, a. s., was made pursuant to Article XI. par. 15 of the applicable Articles of Association of company JAVYS, a. s., in accordance with the resolution of the JAVYS, a.

(254) Press Releases » The decommissioning stage of the V1 NPP has started

The Nuclear Regulatory Authority of the Slovak Republic (ÚJD SR) has issued a resolution about the approval of the first stage of decommissioning the V1 NPP. On Tuesday, the 19th of July 2011 the ÚJD SR has issued resolution Nr.

(255) Press Releases » The JAVYS a. s.

     The JAVYS, a. s. Company has got a significant presence in Central Europe and with its responsible and competent provision of activities in the field of back end of the nuclear energy industry emphasizing the safety, quality and protection of the environment; it is a respected partner also for foreign companies.

(256) Press Releases » The Ministry of Economics made changes in the management of JAVYS

Based on the resolution by the only shareholder, from 20.6.2011, Mr. Ing. Ján Horváth was appointed Chairman of the Board of Directors and at the same time Chief Executive Officer of JAVYS, by the Ministry of Economics of the Slovak Republic.

(257) Press Releases » The V1 NPP Cooling towers have been demolished

Four cooling towers of the former nuclear power plant V1 in Jaslovské Bohunice have been demolished. Demolition works lasted 272 working days, the last piece fell on the ground today.

(258) News » Today, company JAVYS, a.s. commemorates 14 years of its successful existence

Based on the decision of the Government of the Slovak Republic on privatization of company Slovenské elektrárne, a.s., decisions of the National Property Fund and after fulfilling all conditions, the contracts and permits, based on which company GovCo, a.

(259) Press Releases » Transport and disposal of FCCs in the first half of 2018

85 pieces of fibre concrete containers (FCCs) were transported to and disposed of at the National Radwaste Repository in the first half of 2018.

(260) Press Releases » Transport of the last steam generator

Company JAVYS transported the last of twelve 145-tonne steam generator from the decommissioned V1 NPP in Jaslovské Bohunice. Transport of steam generators was a “unique” activity in the history of Slovakia and the V1 NPP decommissioning process now continues in the primary circuit.